Newfield completed a very successful 130,000 square foot base building renovation and office fit-out project, changing use of the space from data center to offices. New windows were introduced to three sides of the building and the entire interior was upgraded in terms of HVAC and Electrical service. Site work included demolition of a neighboring building and surface parking for 500 cars. The 4.5 month project was completed on schedule even through various unforeseen conditions appeared. Asbestos appeared in the walls, as the window openings were cut in, requiring immediate abatement. An underground storage tank, large cement pad and various utility lines were encountered during demolition of the adjacent 40,000 square foot building. 100-150 workers were on-site during the project in order to meet Traveler's schedule.